1800 MW PP13 COMBINED CYCLE POWER PLANT

1800 MW PP13 Combined Cycle Power Plant

Installation of Power Island ME&I and Equipment at 1800 MW Power Plant PP13 is undertaken by GAMA Power Systems as construction contractor.

Project Scope consisted of electromechanical installations, pre-commissioning of 6 ea 7FA Gas Turbine, associated Generator and Heat Recovery Steam Generator (HRSG), 6ea. 2ea GE Reheat Double Flow D11 type Steam Turbine, 5ea Generator Step-Up Transformers (GSU), 2ea Air Cooled Condenser Units (each of the units consisted of 42 cells), and installation of Balance of Plant works together E&IC as well as the Process Buildings. In addition, the EPC responsibility of 380 kV GIS Unit as turnkey basis, i.e. engineering, procurement, installation and commissioning of GIS was under GAMA’s scope.

The project is completed within the scope agreed with the Employer in October 2019.

Location Icon
Location
Riyadh, Saudi Arabia
Client Icon
Client
SEC (Saudi Electricity Company)
Contractor Icon
Contractor
Worley Parsons
Duration Icon
Project Duration
51 Months (July 2015 - October 2019)