870 MW ERZIN COMBINED CYCLE POWER PLANT

870 MW Erzin Combined Cycle Power Plant

EPC Contract for 870 MW Erzin Combined Cycle Power Plant is implemented on a turnkey basis.

Combined cycle power plant in one multi-shaft arrangement. Power plant is comprised of two GE 209FB gas turbine, Skoda MTD60 steam türbine, three GE 330H generator, with associated Doosan Heat Recovery Steam Generators.
EPC Contract’s scope covers procurement of all major equipment as well as other auxiliary equipment, and conceptual and detail engineering of the plant, civil and electro-mechanical installation works, test and commissioning works and training of the Employer’s staff.
Location Icon
Location
Hatay, Turkey
Client Icon
Client
EGEMER Elektrik Üretim A.Ş. (AKENERJİ)
Contractor Icon
Contractor
GE-GAMA Power Systems Inc. Consortium
Duration Icon
Project Duration
34 Months (October 2011 - August 2014)