ERDEMIR-ERENCO COGENERATION POWER PLANT – HRSG MODIFICATION

Erdemir-Erenco Cogeneration Power Plant – HRSG Modification

Modification of 2 existing HRSG, were erected by BWG in 1997, by adding a new HP two pressure level for steam generation.

Project is completed 45 days before the date on the contract.

Location Icon
Location
Karadeniz Eregli, Turkey
Client Icon
Client
Erdemir – Erenco
Duration Icon
Project Duration
18 Months (February 2004 - August 2005)